SHUANGSHITONG — solid waste recycling equipment
احصل على عرض سعر
الرئيسية/المدونة/الخدمات اللوجستية
الخدمات اللوجستية

شحن آلة تمزيق: التحميل والرفع والأساس

A shredder is a heavy, top-heavy box with a rotating mass. How it is packed decides whether it arrives aligned, and the foundation decides whether it stays that way.

Container loading

A double-shaft shredder up to about 1,600 mm chamber width fits in a 40 ft high-cube with the hopper removed. Above that, the machine goes flat-rack or break-bulk. Ask for the loading drawing before the deposit, because the answer changes the freight cost by a factor of two.

  • Machine chocked and welded to the container floor, not just strapped.
  • Cutters immobilised with a wooden wedge plus a steel strap; a shaft that turns in transit destroys the seals.
  • Control panel crated separately with the VFDs, never left loose in the chamber.
  • Wear parts and the manual in a marked crate that is loaded last.

Lifting

Lift on the four designated lugs only. Slings under the chamber crush the base frame and, worse, bend the discharge conveyor mounts. The centre of gravity sits high and toward the drive side, so a single-point lift will rotate the machine.

Foundation

Three details decide whether the machine runs level after six months:

  • A reinforced concrete slab sized to the machine weight plus 30%, isolated from the building slab.
  • Grout pockets under the base frame, so the machine sits on grout rather than on shims alone.
  • A discharge trench or conveyor pit designed before the slab is poured. Retrofitting one means cutting the slab under a running machine.

Send us the site drawing before shipping and we return a foundation drawing with anchor positions and load figures. It costs nothing and saves the most common commissioning delay.

Ask about this application Back to blog